Eskom Holdings Limited plans to construct 9 high voltage transmission lines and associated infrastructure from the high voltage yard (HV yard) at the proposed new nuclear power station site at Bantamsklip, which is situated south-east of Pearly Beach in the Western Cape.

 

ARCUS GIBB (Pty) Ltd has been appointed as the independent environmental assessment practitioner (EAP) to undertake the Scoping and Environmental Impact Assessment (EIA) for the proposed project while NMA Effective Social Strategists (Pty) Ltd will conduct the associated public consultation process. The EIA will conform to the Environmental Impact Assessment Regulations published in Government Notices R385 to R387 of 21 April 2006 in terms of Section 24 (5) of the National Environmental Management Act (Act No. 107 of 1998).

 

The proposed project entails the construction of 9 Transmission lines from the HV-yard at the proposed new Nuclear Power Station site at Bantamsklip with the related and associated infrastructure. This comprises:

 

  • 4 x 765 kV lines from the Bantamsklip site – Kappa substation;
  • 4 x 400 kV lines from the Bantamsklip site – Bacchus substation;
  • 4 x 400 kV lines from the Bacchus substation – Kappa substation;
  • 1 x 400 kV line from the Bacchus substation – Muldersvlei substation; and
  • The extension of the Bacchus substation.

 

Due to the number of lines and the extent of the study area, the project has been divided into two separate EIA applications:

 

Application 1 (DEAT Reference No: 12/12/20/1223) includes the following:

  • 4 x 765 kV lines from the Bantamsklip site – Kappa substation;

 

Application 2 (DEAT Reference No: 12/12/20/1224) includes the following:

  • 4 x 400 kV lines from the Bantamsklip site – Bacchus substation;
  • 4 x 400 kV lines from the Bacchus substation – Kappa substation;
  • 1 x 400 kV line from the Bacchus substation – Muldersvlei substation; and
  • The extension of the Bacchus substation.

 

 

Should you have any comments regarding the proposed project, please submit them in writing to:

NMA Effective Social Strategists
Attention: Theo Hansford
E-mail: theoh@nma.org.za
PO Box 32097, Braamfontein, 2017
Tel: 011 447 9737
Fax: 086 601 0381

 

 Documents available for Bantamsklip EIA application 1
 TitleDescriptionSize 
Cover Page Vol 1133.07 KBDownload
Cover Page Vol 2133.13 KBDownload
Cover pageVol 3133.12 KBDownload
Chapter 1 INTRODUCTION76.76 KBDownload
Chapter 2DETAILS OF ROLEPLAYERS15.36 KBDownload
Chapter 3DESCRIPTION OF THE PROPOSED DEVELOPMENT2.14 MBDownload
Chapter 4NEED AND DESIRABILITY FOR THE PROPOSED DEVELOPMENT28.08 KBDownload
Chapter 5PROJECT ALTERNATIVES1.15 MBDownload
Chapter 6LEGAL AND POLICY CONTEXT130.44 KBDownload
Chapter 7SCOPE OF ENVIRONMENTAL INVESTIGATIONS93.82 KBDownload
Chapter 8BASELINE ENVIRONMENT1 020.18 KBDownload
Chapter 9IDENTIFICATION OF ISSUES AND IMPACTS1.14 MBDownload
Chapter 10SENSITIVITY MAPPING ANALYSIS2.55 MBDownload
Chapter 11CONCLUSIONS AND RECOMMENDATIONS629.27 KBDownload
Chapter 12PLAN OF STUDY FOR EIA1.37 MBDownload
Chapter 13REFERENCES50.11 KBDownload
   
 Appendices
 TitleDescriptionSize 
Appendix A: DEAT Acceptance Letter – 22 August 2008 80.59 KBDownload
Appendix B: Eskom Guidelines for Erosion Control and Vegetation Management341.01 KBDownload
Appendix C:Eskom Gate Guidelines568.07 KBDownload
Appendix D:Proposed Bantamsklip - Kappa Alternative Corridors (Maps) 116.60 MBDownload
Appendix D:Proposed Bantamsklip – Kappa Alternative Corridors (Maps) 2 16.83 MBDownload
Appendix D:Proposed Bantamsklip – Kappa Alternative Corridors (Maps) 3 17.29 MBDownload
Appendix D:Proposed Bantamsklip – Kappa Alternative Corridors (Maps) 4 16.79 MBDownload
Appendix D:Proposed Bantamsklip – Kappa Alternative Corridors (Maps) 5 18.58 MBDownload
Appendix D:Proposed Bantamsklip – Kappa Alternative Corridors (Maps) 6 20.44 MBDownload
Appendix D:Proposed Bantamsklip – Kappa Alternative Corridors (Maps) 718.82 MBDownload
Appendix D:Proposed Bantamsklip – Kappa Alternative Corridors (Maps) 8 19.72 MBDownload
Appendix D:Proposed Bantamsklip – Kappa Alternative Corridors (Maps) 9 17.64 MBDownload
Appendix D:Proposed Bantamsklip – Kappa Alternative Corridors (Maps) 1017.45 MBDownload
Appendix D:Proposed Bantamsklip – Kappa Alternative Corridors (Maps) 1320.64 MBDownload
Appendix D:Proposed Bantamsklip – Kappa Alternative Corridors (Maps) 1419.23 MBDownload
Appendix D:Proposed Bantamsklip – Kappa Alternative Corridors (Maps) 1918.55 MBDownload
Appendix D:Proposed Bantamsklip – Kappa Alternative Corridors (Maps) 2017.89 MBDownload
Appendix E:Preliminary Analysis of the Applicable National and Provincial Legislation78.53 KBDownload
Appendix F:Interested and Affected Persons Database429.50 KBDownload
Appendix G:Newspaper Advertisements - Breede River Gazette 1 August 2008533.54 KBDownload
Appendix G:Newspaper Advertisements - Caledon Kontrienuus 1 August 2008479.51 KBDownload
Appendix G:Newspaper Advertisements - Die Burger 2 August 2008464.49 KBDownload
Appendix G:Newspaper Advertisements - Elgin Grabouwer 1 August 2008556.75 KBDownload
Appendix G:Newspaper Advertisements - Hermanus Times375.27 KBDownload
Appendix G:Newspaper Advertisements - Kaapse Son 1 August 2008443.29 KBDownload
Appendix G:Newspaper Advertisements - Overberg Venster398.36 KBDownload
Appendix G:Newspaper Advertisements - Paarl Post 31 July 2008521.57 KBDownload
Appendix G:Newspaper Advertisements - Standford River Talk - August 2008583.71 KBDownload
Appendix G:Newspaper Advertisements - Stellenbosch - Franschoek Gazette446.07 KBDownload
Appendix G:Newspaper Advertisements - Suidernuus 1 August 2008525.85 KBDownload
Appendix G:Newspaper Advertisements - Weekend Argus - 2 August3.50 MBDownload
Appendix G:Newspaper Advertisements - Witzenberg Herald - 1 August 2008418.06 KBDownload
Appendix G:Newspaper Advertisements - Worcester Standard - 31 July 2008434.23 KBDownload
Appendix G:Newspaper Advertisements - Langeberg Bulletin 1 August 2008551.35 KBDownload
Appendix H:Background Information Documents405.99 KBDownload
Appendix I:Notes from Focus Group Meetings359.75 KBDownload
Appendix J:Issues and Response Report1.71 MBDownload
Appendix K:Land Capability Impact Assessment1.57 MBDownload
Appendix L:Flora Impact Assessment6.39 MBDownload
Appendix M:Fauna Impact Assessment - Report 26.09 MBDownload
Appendix M:Fauna Impact Assessment - Appendix 29.09 MBDownload
Appendix N:Avifauna Impact Assessment603.21 KBDownload
Appendix O:Social Impact Assessment - Annexture C - Muldersvlei-Bacchus Maps1 011.50 KBDownload
Appendix O:Social Impact Assessment - Annexture C - Muldersvlei - Bacchus maps859.46 KBDownload
Appendix O:Social Impact Assessment - Annexture D - Bantamsklip - Bacchus maps1.83 MBDownload
Appendix O:Social Impact Assessment - Annexure D - Bantamssklip - Bacchus maps1.56 MBDownload
Appendix O:Social Impact Assessment - Annexure E - Bantamsklip - Kappa Maps1.99 MBDownload
Appendix O:Social Impact Assessment - Annexture E - Bantamsklip - Kappa Maps1.70 MBDownload
Appendix O:Social Impact Assessment - Bantamskip Draft SIA Scoping Report1.48 MBDownload
Appendix P:Heritage Impact Assessment1.00 MBDownload
Appendix Q:Visual Impact Assessment - Final Bantamsklip30.13 MBDownload
   
 Appendix R - Project Specialist CV's
 TitleDescriptionSize 
Avifauna Specialist - Chris van RooyenCV101.25 KBDownload
Avifauna Specialist - Chris van RooyenDeclaration of Independence49.49 KBDownload
Fauna specialist - James HarrisonCV109.52 KBDownload
Fauna specialist - James HarrisonDeclaration of Independence85.72 KBDownload
Flora specialist - Nick HelmeCV10.17 KBDownload
Flora specialist - Nick HelmeDeclaration of Independence48.98 KBDownload
Heritage specialist - Lita WebleyCV8.39 KBDownload
Heritage specialist - Lita WebleyDeclaration of Independence49.01 KBDownload
Heritage specialist - Tim HartCV306.77 KBDownload
Heritage specialist - Tim HartDeclaration of Independence14.75 KBDownload
Land Capability specialist - Bernardt SchlomsCV36.71 KBDownload
Land Capability specialist - Bernardt SchlomsDeclaration of Independence1.03 MBDownload
Land capability specialist - Francois du PlessisCV64.73 KBDownload
Land capability specialist - Francois du PlessisDeclaration of Independence107.18 KBDownload
Land capability specialist - Johann EngelbrechtCV6.63 KBDownload
Land capability specialist - Johann EngelbrechtDeclaration of Independence1.12 MBDownload
Land capability specialist - Johann MurrayDeclaration of Independence1.27 MBDownload
Land capability specialist - Johann MurrayCV27.44 KBDownload
Land capability specialist - Johannes LampbrechtsCV14.13 KBDownload
Land capability specialist - Johannes LampbrechtsDeclaration of Independence167.11 KBDownload
Legal advisor - Nick SmithCV129.67 KBDownload
Legal advisor - Nick SmithDeclaration of Independence412.58 KBDownload
Legal advisor - Richard SummersCV109.65 KBDownload
Legal advisor - Richard SummersDeclaration of Independence425.84 KBDownload
Social specialist - Tony BarbourCV64.36 KBDownload
Social specialist - Tony BarbourDeclaration of Independence18.17 KBDownload
Visual specialist - Liesel StokesCV104.78 KBDownload
Visual specialist - Liesel StokesDeclaration of Independence77.38 KBDownload
Visual specialist - Stephen SteadCV49.97 KBDownload
Visual specialist - Stephen SteadDeclaration of Independence45.82 KBDownload
   
  EIA Team Experience and Declarations of Independence
   
 Scoping phase Public and Key Stakeholder Meeting Minutes
 TitleDescriptionSize 
Cape Town Key Stakeholders Meeting16 March 2009212.72 KBDownload
Robertson Public Meeting16 March 2009236.87 KBDownload
Villiersdorp Public Meeting17 March 2009200.16 KBDownload
Caledon Public Meeting18 March 2009229.98 KBDownload
Stanford Public Meeting19 March 2009268.10 KBDownload
Pearly Beach Public Meeting21 March 2009270.07 KBDownload
Bredasdorp Public Meeting23 March 2009263.74 KBDownload
Swellendam Public Meeting24 March 2009211.25 KBDownload
Barrydale Public Meeting25 March 2009194.54 KBDownload
Riviersonderend Public Meeting26 March 2009207.00 KBDownload
Wolseley Public Meeting30 March 2009183.10 KBDownload
Worcester Public Meeting31 March 2009193.97 KBDownload
Koo Public Meeting1 April 2009177.41 KBDownload
Touws River Public Meeting1 April 2009194.94 KBDownload
Wellington Public Meeting2 April 2009261.76 KBDownload
Tesselaarsdal Public Meeting3 April 2009223.15 KBDownload
Presentation 6.57 MBDownload
   
 Focus Group Meetings and Multi-Stakeholder Workshops
   
 Technical Information
   
 Public Participation Team members
 TitleDescriptionSize 
Julian DrewCV91.78 KBDownload
Julain DrewDeclaration of Independence19.64 KBDownload
Nomi MuthialuCV130.87 KBDownload
Nomi MuthialuDeclaration of Independence19.36 KBDownload
   
  Login